Letter to Financial Institution  
Payment Schedule
Water Requirement
Project Cost Power & Ethanol
Statement of Expenditure to run the plant
Sale & Viability statement
Project Report
Certificate of Incorporation
Certificate of Sale Tax Registration
IEM
MPCB Consent
Noc of Sugar Commissioner
Noc of Gram Panchayat
Provisional Balance Sheet 2001-02
Project Plan
7/12 of Land
     

Water Requirement


M/s. Chintamani Agrotech (India) Ltd.
Village Biljora, Tha. Mahagaon, Dist. Yavatmal


 

 

Season

 

Off Season

Total

S.No

Description

M /hr

M/day

Day

M /hr

M /day

Day

M / Annum

 

 

 

 

operation

 

 

operation

 

                 

1

Sugar

4

96

200

--

--

--

18,200

2

Cogen

 

 

 

 

 

 

 

 

DM Plant

12

233

200

8

192

130

82,560

 

CW system

80

1020

200

120

2880

130

758,400

3

Ethanol

 

 

 

 

 

 

 

 

Process

28

672

200

28

672

130

221,760

 

CW system

55

1320

200

55

1320

130

435,600

 

 

 

 

 

 

 

 

Total

1,517,520

 


Total Makeup water Required = 1,517,520 M /annum
                                                   (or 15175 lakh litres / annum)

Average daily consumption    =  42.96 lakhs Litres per day during season &
                                                    50.64 lakhs Litres per day during off season.

The ethanol numbers have been taken on the basis of data furnished by Ethanol plant manufacture.
It is also generally mentioned Sugar process make up is assumed zero due to water generation from process.

 
 

                                             Copyright CAIL - 2007                                                                                      Site Designed & Developed by Purple Haze Multimedia