Period |
in Rs. Millions |
|
Remarks |
| |
|
|
|
January '03 |
60.0 |
|
Civil works starting |
February |
85.0 |
|
Advances for major equipments |
March'03 |
60.0 |
|
Advances for other equipments |
April'03 |
80.0 |
|
Structural and Civil works |
May'03 |
90.0 |
|
Part payment of equipments |
June'03 |
125.0 |
|
do |
July'03 |
100.0 |
|
do |
August'03 |
100.0 |
|
Civil works completed |
September'03 |
150.0 |
|
Erection of Boiler & Ethanol in progress |
October'03 |
150.0 |
|
do |
| November'03 |
200.0 |
|
Balance of plant completion |
December'03 |
200.0 |
|
Commissioning of Ethanol plant |
January'04 |
250.0 |
|
Turbine erection in progress |
February'04 |
100.0 |
|
do |
March'04 |
60.0 |
|
Switchyard erection completion |
April '04 |
80.0 |
|
Commissioning of power plant |
May'04 |
150.0 |
|
Margin money |
June'04 |
30.0 |
|
Staff quarters ready for occupation |
| |
Total |
2070.0 |
|
|
| |